India's Green Grid Dreams Face Reality Check: Can Wires Keep Up With Watts?
India's ambitious drive to build out its power transmission network is hitting a tough patch, with grid congestion forcing renewable energy projects to slash generation by as much as 50%. A recent ICRA report highlighted that transmission bottlenecks are severely impacting solar projects, particularly across the western and northern regions, where over 300 Gigawatt-hours of green power were curtailed in the first quarter of 2026 alone. This unexpected brake on green power, despite massive investment plans of over ₹9.15 lakh crore by 2032, threatens the country's clean energy targets and is making developers rethink their strategies.